This scheme saw nmcn deliver a two phase student accommodation complex in the heart of Sheffield city centre. The two buildings incorporated over 750 student bedrooms constructed over an eighteen month period. Innovative design and construction techniques promise to achieve a BREEAM Excellent standard for both buildings. Phase one of the scheme housed four student blocks and provided 535 apartments in four- and five-bed clusters over seven floors. Each bedroom has its own en-suite, while each cluster included a communal living room and kitchen area. Phase two saw the construction of an eleven-storey block with an adjoining glass corridor to a communal court yard area.
The site was originally a car park located on Denby Street, situated opposite Sheffield United’s football stadium. It is also surrounded by other businesses, student accommodation and private dwellings, making for an extremely tight site and work area. This led to significant logistical challenges throughout the course of the project. Our main consideration was getting materials to site efficiently and then distributing it around the scheme once delivered.
The solution to overcome this challenge was two-fold. Firstly, we meticulously planned how we would get materials to site in the most efficient way possible. We then detailed out how material would be handled when on site in order to distribute them to the various work areas. This resulted in our delivery team securing off site storage space, with one of our supply partners, to transit materials on a ‘just in time’ basis. This led to us maximising the amount of available space on site and decluttering work areas to create greater production efficiency.
Secondly, we identified a need for two tower cranes. A detailed hook time analysis, carried out as part of our logistics planning process, highlighted that the use of two cranes would create distribution efficiencies. This allowed us to move materials around site effectively, both horizontally and vertically across the two buildings.
Our solutions resulted in the efficient and effective delivery of materials when required. We limited the amount of space required to store materials, which led to the safe and productive day to day operations of the site. Overall the detailed planning and execution of our logistics strategy significantly contributed to the handover of more than 750 bedrooms. In turn, this allowed the clients student intake to occupy their rooms prior to the commencement of the academic year.
Sirius Minerals plc
Potash Mine Highway & Enabling Works Phases 1 & 2
Highways and enabling works for a new £3.2bn polyhalite mine within the North York Moors national park. nmcn undertook a range of enabling works for the new mine, including: Tree and vegetati...
Read the case studyStephen George and Partners
Stephen George and Partners
Stephen George and Partners commissioned nmcn to deliver their new state of the art architectural practice. The building has been located on the final available plot within the Grove Business Park d...
Read the case studyNottingham University Hospitals NHS Trust
Queens Medical Centre
Following the successful completion of the boiler plant upgrade project at Nottingham City Hospital, we were awarded the new plant room and medical ward fit out scheme at the Queens Medical Centre in ...
Read the case study